The construction of the raw water pipeline for the Liberia Water and Sewer Corporation (LWSC) is more than 50 percent complete and on schedule to be completed in September 2020.
The US$18 million pipeline will draw water from the dam of the Mt. Coffee Hydropower Plant to the White Plains Water Treatment Plant. The project will save LWSC approximately US$780,000 a year in electricity costs as the water will be transported using gravity instead of pumping water into the treatment plant from the St. Paul River. The undertaking by the Millennium Challenge Account-Liberia (MCA-L) will replace the original 36-inch diameter pipeline that was destroyed during Liberia’s civil war with a new 48-inch diameter pipeline.
According to Jurgen De Moor, project engineer for Belgium-based contractor Denys, all 820 pipes have now arrived on site after being shipped from the manufacturer in India. Denys has also cleared 98 percent of the route along the pipeline and the pipes have been strung along, awaiting the process of trenching, pipe laying, and backfilling, which has already begun in some areas.
Compensation of those affected by the project is nearing completion, with 54 of the 55 persons whose properties fall in the pipeline’s right of way having been paid. Additionally, a financial management training for individuals receiving compensation is ongoing and expected to end this month.
De Moor said two types of pipes are being used – ones that will be exposed and others that will be buried.
“The exposed pipes are made of steel and have epoxy coating on the outside and inside, while the buried pipes are made of ductile iron and contain cement lining inside and bituminous coating outside,” he noted. “The coatings will help protect bacteria from penetrating the pipes and contaminating the water while also preventing corrosion of the pipes.”
The 5-km long pipeline project has already employed 114 persons, with 79 coming from the surrounding communities of White Plains and Harrisburg.
As part of the MCA-L mandate of promoting gender and social inclusion, 21 percent of the workers hired by Denys are women – a much higher percentage than the industry standard of under 10 percent.
One of the women working on the project is Barbara A. Debah, a quality assurance officer at Denys who obtained her civil engineering degree from Stella Maris Polytechnic University.
“One of my tasks is to make sure that the pipes are in good condition, specifically the lining and coating,” Debah said, noting that for the pipes to have a long lifespan, they should be free of cracks and rust before they are placed in the ground.
When completed, the pipeline is not only expected to save LWSC money; it will also improve the reliability and quality of water supply to Monrovia. The current location of LWSC’s intake pipe results in poor water quality and salty water during the dry season when the St. Paul River level is low, as water from the Atlantic Ocean washes back into the river. Instead of retrieving water from downstream and closer to the ocean, the pipeline will draw water from the reservoir upstream.
Funded by the Millennium Challenge Corporation for the Government of Liberia, the raw water pipeline is part of the Energy project under the compact, which is committed to reducing poverty in Liberia by promoting economic growth and inclusion.
About MCA-L: In October 2015, the Government of the United States of America, through its development agency, Millennium Challenge Corporation, provided a grant of US$257 million to Liberia. MCA-L is an independent, legal, and autonomous agency of the Government of Liberia created by the legislature to administer the compact projects, which address the lack of access to reliable and affordable electricity and inadequate road infrastructure. Learn more about MCA-L at .
Sign in
Sign in
Recover your password.
A password will be e-mailed to you.
Water Pipeline Construction More Than 50% Complete
Prev Post
7 Comments
Leave A Reply
Cancel Reply
You made some decent points there. I did a search on the subject and found most individuals will consent with your blog.
WONDERFUL Post.thanks for share..extra wait .. …
Hi my family member! I want to say that this post is awesome, great written and come with approximately all vital infos. I?¦d like to peer extra posts like this .
I’m extremely impressed along with your writing abilities as neatly as with the layout for your weblog. Is this a paid topic or did you customize it your self? Either way keep up the excellent high quality writing, it is rare to peer a great blog like this one nowadays..
I appreciate, cause I found exactly what I was looking for. You have ended my 4 day long hunt! God Bless you man. Have a great day. Bye
Heya i’m for the primary time here. I found this board and I in finding It truly helpful & it helped me out much. I am hoping to give something back and help others like you aided me.
I’d must test with you here. Which isn’t something I often do! I get pleasure from studying a publish that can make individuals think. Additionally, thanks for allowing me to comment!